Local market / East Lampeter Township, Lancaster County, Pennsylvania

Clark’s 48,000-square-foot office reuse shows the value of phased conversion

A former Lancaster Mennonite school building became a fully occupied Clark Associates office through a multiyear, phased redevelopment.

A completed conversion with a documented timeline

Clark Associates has completed a 48,000-square-foot office building at 2257 Old Philadelphia Pike, expanding its Lancaster corporate campus through the reuse of the former Lancaster Mennonite Locust Grove property. The company marked the project with an October 27 open house and published the completed timeline on November 19. [1]

According to Clark, the company purchased the former campus building at the end of 2021. Phase one construction began in 2024. The first offices and conference rooms opened in summer 2025, and phase two was completed in June 2026, bringing the full building into use. [1]

That sequence matters. It turns a broad redevelopment announcement into a practical Lancaster County example of phased adaptive reuse: acquire an existing institutional property, work through land-use planning, improve it in stages and occupy usable portions before the entire conversion is finished.

The land-use record started before construction

East Lampeter Township Planning Commission minutes from May 2021 document the early proposal for the 2257 Old Philadelphia Pike property. At the time, the site consisted of two parcels totaling 12.6 acres and was still used as the Locust Grove school campus. The applicant described a conceptual plan to rezone the property from residential to light industrial for future Clark Associates expansion. The minutes also recorded an expectation that the existing building would first be occupied as offices and that a fuller buildout would take several years. [2]

That early description aligns with the timeline the company has now reported, but the documents serve different purposes. The 2021 minutes describe a concept under review. Clark’s 2026 announcement describes work that has been completed and occupied. Keeping those statuses separate prevents a proposed feature from being reported as a finished one.

The property’s previous use also has a long local history. Lancaster Mennonite says the school acquired a 10-acre tract at 2257 Old Philadelphia Pike in 1960, moved students into a new building there in 1964 and expanded the building over the following decades. [3] The office conversion therefore reused a structure that had already evolved through multiple additions and generations of occupancy.

Phasing can reduce the all-or-nothing risk

A vacant institutional building can present an owner with two extreme choices: complete every improvement before occupying anything, or leave the property unused while a larger redevelopment is designed. Clark’s reported timeline shows a third path.

Opening the first office spaces in summer 2025 allowed the company to use part of the investment before phase two was complete. A phased approach can:

  1. Match construction spending to operational priorities.
  2. Move teams as finished areas become available.
  3. Test circulation, shared spaces and building systems before full occupancy.
  4. Reduce the period during which the entire property produces no operational value.
  5. Keep later work coordinated with a broader campus plan.

Phasing is not automatically cheaper. Temporary separations, repeated mobilization and work around occupied areas can add cost and complexity. The advantage is flexibility, especially when an owner-user has a long planning horizon and can define which spaces must open first.

The completed building supports several functions

Clark says the converted building now houses merchant, procurement operations and research-and-development employees. It also includes a company cafe, gymnasium, courtyard, meeting areas and a research-and-development center. [1]

Those uses help explain why a former school could be a workable starting point. Institutional buildings often contain larger common rooms, circulation areas and a mix of room sizes. They can also require substantial changes to mechanical systems, technology, accessibility, fire protection and interior layouts before they function as modern offices.

The valuable lesson is not that every school is an easy office conversion. It is that the existing structure should be evaluated against the owner’s program before demolition or a ground-up building is treated as the default.

For an owner-user, the due-diligence questions include:

  1. Which structural grids and room depths support the intended work?
  2. Can the electrical, data and mechanical systems handle the new occupancy?
  3. What accessibility and life-safety upgrades are required?
  4. How will parking, deliveries and employee circulation work across the larger site?
  5. Which existing features can be retained without compromising operations?
  6. Can the property be occupied in phases without disrupting construction?

Do not confuse the completed conversion with the entire campus plan

East Lampeter Township’s October 2024 minutes describe a broader land-development plan at the address. That plan included renovation of an approximately 42,000-square-foot former school building, a separate three-story 36,000-square-foot office building, a solar field, parking, utilities and stormwater facilities. The Board of Supervisors conditionally approved that plan subject to review comments. [4]

Clark’s current announcement describes the completed 48,000-square-foot building. It does not state that every element in the broader 2024 plan has been constructed. The two square-foot figures also come from documents prepared at different stages and should not be treated as measuring an identical scope.

That distinction is important for anyone researching commercial projects. A municipal approval establishes what a plan may move toward under stated conditions. A company completion notice establishes what the company says is open. A reliable property analysis checks both.

A Lancaster County owner-occupancy lesson

This project is especially relevant to businesses considering owner-occupied property. The real estate decision was tied to a long-term campus need, not simply to filling a generic office vacancy. The buyer could plan the property around its own teams, amenities and future growth while accepting a multiyear entitlement and construction process.

A business comparing an existing building with new construction should model at least four timelines:

  1. Acquisition and due diligence.
  2. Zoning, land-development and permitting.
  3. Construction phases and occupancy approvals.
  4. Team moves and operational ramp-up.

The Clark timeline shows why those schedules should be integrated. The purchase occurred years before the full building opened, yet partial occupancy began before final completion.

For Lancaster County, the result puts a former school property back into productive use and expands an established corporate campus without requiring the completed office program to wait for every future site element. It is a useful example of adaptive reuse because the public record now connects the original concept, municipal review and completed occupancy.

Sources & further reading

How does this affect your property?

Bring your questions about buying, leasing or owning commercial space.

Find business space · Sell or lease a property · Industrial and flex space

Talk with Zach